Building a House in PIK: The 16 Stages from Planning to Handover

The real order of work, and what to check at each stage.

Building a house in Pantai Indah Kapuk (PIK) is not like building in most places. The ground is soft and layered, the water table is shallow, and almost every house stands on deep driven piles. The order of the work, and the checks made at each stage, decide the result long before any finishes are visible.

These are the sixteen stages we follow, from the first conversation to the years after handover. You don't need to memorise them. Use them to understand what is happening on your site, and what is worth asking your contractor.

Planning

1. Assessment and alignment

We start by understanding your plot, your goals and needs, your timeline, your budget range and your constraints, before anyone commits to a design or a price.

2. Architectural design

The architectural design is prepared by one of our partner architects. If you already have an architect, we work alongside them.

Bringing the architect and the contractor together early matters, because the budget decides how large a house, and what kind of house, can realistically be built. A design developed without anyone costing it often ends in major revisions: floor area cut, materials changed or details dropped, after design time and fees have already been spent. That is why we work with the architect from this stage, so that the floor area, form and specification of the house stay in line with your budget. The design is also coordinated with the structure and the mechanical, electrical and plumbing (MEP) services, so there are no surprises when the construction drawings and cost estimate are prepared. If you are unsure whom to call first, see Building a House: Contractor or Architect First?

3. Soil investigation

The ground beneath your plot is investigated with cone penetration tests and boreholes. The foundation is designed from data, not assumptions. More in Soil Investigation for a House in PIK.

4. Structural design and cost estimate

All structural drawings and calculations are prepared by an independent structural consultant we trust, PT Cipta Sukses, to the Indonesian standards SNI 8460:2017 (geotechnical design), SNI 2847:2019 (structural concrete) and SNI 1726:2019 (earthquake resistance). If you already have a structural design, we still ask the consultant to review it before construction starts. Together with the architect, we align the design intent, structural safety and a clear, itemised cost estimate. How to read and compare estimates is covered in Comparing Contractor Quotes in Jakarta, and how to choose a cost arrangement, including the cost-plus-fee contract we recommend, in Your House-Building Budget.

5. Building permit

The building permit (Persetujuan Bangunan Gedung, which replaced the old IMB) is applied for using the final architectural and structural drawings, so your house is legal from the start.

Foundations

6. Site preparation

Hoarding, setting out and marking the building lines. Before piling starts, the condition of neighbouring buildings is recorded with photos and notes, including existing cracks, as a shared reference throughout construction.

7. Piling

In our experience in PIK, house piles range from about 15 to 38 metres deep, depending on the soil layers and the building's loads. The heavier the load and the longer the pile, the larger the pile section usually needs to be, both to carry the design load and to withstand the stresses of driving. We use the longest pile segments that site access and the piling rig allow, so there are as few joints as possible, because joints are a weak point in a pile. More in Pile Foundations for a House in PIK.

8. Pile testing: PDA and PIT

Once piling is finished, and while the rig is still on site, we bring in a separate pile-testing company, independent of the structural consultant, for two complementary tests:

  • PDA (Pile Driving Analyzer, ASTM D4945) on test piles, to estimate pile capacity.
  • PIT (Pile Integrity Test, ASTM D5882), to check pile integrity and detect defects such as cracks or breaks.

If the results show that extra piles are needed, they are driven straight away, without the cost of bringing the rig back a second time.

9. Excavation and dewatering

Excavations for pile caps, ground beams, the underground water tank and any basement are kept dry by controlled dewatering. Concrete cast in a wet excavation can mix with water and mud, which lowers its strength and can leave it honeycombed. Pumping must not be excessive either, because it can cause the surrounding ground to settle, including under neighbouring buildings.

10. Substructure

The pile heads are cut, then the pile caps, ground beams and ground floor slab are cast. For an underground water tank or basement, groundwater pushes from the sides and lifts from below, so watertight concrete, construction joint details and waterproofing are planned from the start, not patched after a leak. How we build and test the underground water tank and septic tank is explained in Underground Water Tank and Septic Tank for a PIK House.

Building

11. Superstructure

Columns, beams, slabs, stairs and roof. Every concrete pour comes with a slump test (SNI 1972:2008) and a concrete temperature check. Test cylinders are taken and crushed in a laboratory (SNI 1974:2011), with 28 days as the reference age for the design strength.

12. Walls, services and waterproofing

Masonry walls; mechanical, electrical and plumbing installations; and waterproofing of bathrooms, balconies and the roof.

13. Finishes

Finishes follow the architect's and interior designer's designs. We also coordinate all interior and fit-out suppliers, such as built-in joinery, kitchens and decorative lighting, so that their schedules, dimensions and fixing points line up with the structure and the MEP services. You don't have to manage the suppliers' schedules yourself.

Completion

14. Testing before handover

Work is supervised in a structured way, and every critical stage passes a quality check before the next begins. For example, waterproofing is flood-tested before it is covered by finishes. Before handover, every installation is tested.

15. Handover

Handover includes as-built drawings, so that future maintenance and alterations can be done correctly.

16. After handover

For the buildings we build, our team makes a maintenance visit once a year, before the rainy season. Our responsibility does not end when the keys change hands.

What to check, whoever your contractor is

  • Have the architect and the contractor discussed the budget before the design is fixed?
  • Does the soil investigation include boreholes, not only cone penetration tests?
  • Is the structure designed and checked by a structural consultant, to stated Indonesian standards?
  • Are the piles tested with PDA and PIT by a tester independent of the builder?
  • Is the condition of neighbouring buildings recorded before piling?
  • Does every concrete pour come with a slump test and test cylinders?
  • Will you receive as-built drawings at handover?

If you are planning a house in PIK or North Jakarta, see how we work, or talk to us before the design and budget are fixed.

Frequently asked questions

What are the stages of building a house in PIK?

In outline: planning (assessment, architectural design, soil investigation, structural design and cost estimate, building permit), foundations (site preparation, piling, pile testing, excavation and dewatering, substructure), building (superstructure, walls and services, finishes), then testing, handover and aftercare.

Why does the soil investigation come before the structural design?

Because the type, size and depth of the piles are designed from the soil data. On PIK's soft ground, designing a foundation without adequate soil data is guesswork.

What are PDA and PIT tests?

PDA (ASTM D4945) estimates the capacity of a pile, while PIT (ASTM D5882) checks its integrity and detects defects such as cracks or breaks. Both are carried out after piling.

What should an owner receive at handover?

As well as a house whose installations have been tested, the owner should receive as-built drawings for future maintenance and alterations.