Pile Foundations for a House in PIK: How Deep, and Why It Matters

Understanding foundations on the soft ground of PIK and North Jakarta.

Piles are the part of a house you never see again once it is built. Yet they decide whether your floors, walls and structure stay level and intact for decades. In Pantai Indah Kapuk (PIK) and the rest of North Jakarta, decisions about piles matter more than in many other places, because of the ground.

This article explains how deep house piles in PIK typically go, what can make that depth wrong, and how you can make sure the decision is made properly.

The ground in PIK and North Jakarta

Much of PIK is built on reclaimed land and former fishponds, over soft coastal clay. A study of a reclamation area near PIK recorded a very soft layer about 5 to 12 metres thick that was still compressing (consolidating) several years after filling was completed.[1]

North Jakarta is also sinking. A researcher at BRIN, Indonesia's National Research and Innovation Agency, puts the average subsidence at about 3.5 cm a year, with the worst-affected points sinking tens of centimetres a year.[2]

For your house, the meaning is simple: the upper layers of ground cannot be relied on to carry the building. Its weight has to be carried down by piles to deeper, stronger ground.

How deep do house piles go in PIK?

In our experience in PIK, house piles range from about 15 metres to 38 metres deep. The range is wide for two reasons. First, the depth of strong ground varies from one plot to the next, even within the same estate. Second, every house carries a different load, depending on the number of storeys, whether there is a basement, and the structural spans.

That is why a figure from the house next door, or from a previous project, cannot simply be applied to yours. The biggest risk is piles that stop too shallow, and in PIK one of the main causes is a layer that looks hard but is not.

False hard layers: the lenses that mislead

Coastal deposits in PIK and North Jakarta are rarely arranged neatly from soft to hard. Within the soft clay there are often lenses: thin, discontinuous layers, usually dense sand or stiff clay, that thin out sideways and can disappear within a few metres. Below a lens, the ground turns soft again. In our experience, lenses like these are fairly common in PIK, and because they are not continuous, soil data from the neighbouring plot cannot be relied on.

During piling, a lens gives high resistance at the pile tip. The criterion for stopping, whether the final set on a driven pile or the hydraulic pressure on a jacking rig, can be met on that lens, so the pile appears to have reached firm ground. Without a soil investigation that goes through the lens and the layers below it, this goes undetected, and the pile is stopped on a bearing layer that is actually too thin.

The problem only appears once the building is standing. When the dead load (the weight of the structure, walls and floors) and the live load (occupants and furniture) act in full, the pile tip can punch through the lens, or the soft layer beneath it compresses under the load the pile passes down.[6] The piles settle, often unevenly from one point to another, and the structure above cracks.

At handover, this damage may not be visible, because early cracks can be hidden by plaster and paint. Within a few years, though, the house starts to look old: diagonal cracks that keep coming back, sloping floors, doors and windows that stick. Damage like this is difficult and expensive to repair, because its source is under the building.

Downdrag: load that comes from the ground

Lenses are not the only reason PIK's ground needs special treatment. In soft soil that is still consolidating or subsiding, an extra force acts on the piles. As the ground around a pile settles, it drags the pile down with it. This is called negative skin friction, or downdrag.

The Indonesian geotechnical design standard, SNI 8460:2017, addresses this directly: negative skin friction must be included as a design load on the pile, and its effect must be set out in the pile foundation design report.[3] For you, this means pile calculations in PIK cannot consider the weight of the house alone. The behaviour of the surrounding ground has to be part of the calculation.

How the right piles are determined

The right pile depth and size come from data, not from habit or a neighbour's numbers. Three steps decide them.

1. A soil investigation on your plot

Everything starts with data from your own plot. On lensed ground like PIK, a cone penetration test alone is not enough, because the cone can stop on a lens. Boreholes with Standard Penetration Tests and laboratory testing show the type of each layer, where the genuinely firm layer lies, and the compressibility of the soft clay needed to calculate downdrag. SNI 8460:2017 requires the investigation to continue to a depth at which all the layers affected by the building's load are known.[3] That way, no soft layer is left hidden below the planned pile tips. Our article on soil investigation in PIK explains this in detail.

2. Calculation by a structural consultant

From that data, the structural consultant calculates the piles your house needs, including downdrag. SNI 8460:2017 sets a minimum safety factor of 2.5 for the bearing capacity of deep foundations.[3] At Rimba, the structural drawings and calculations are prepared by an independent structural consultant, PT Cipta Sukses.

A calculation based on data also prevents the opposite mistake: piles deeper or larger than needed, which means unnecessary material and piling costs.

3. Choosing piles that can reach firm ground

If the soil data shows lenses, the piles must be able to pass through them. There are two common approaches. The first is pre-boring through the lens before the pile is installed. This is a recognised method, but friction between the pile and the soil is reduced over the pre-bored length, so its effect must be allowed for in the design.

The second is to use piles with a larger cross-section. The force needed to install a pile is the resistance at its tip plus the friction along its shaft, and that friction keeps increasing with depth. Meanwhile, the force a pile can take without damage is proportional to its cross-sectional area. So the deeper the firm layer, the larger the pile section needs to be, so that the pile can push through lenses and keep going down to genuinely firm ground that provides the capacity the foundation design requires.

The method and pile size are set by the structural consultant's calculation, based on the soil data and site access.

After installation: PDA and PIT tests

Calculations on paper need to be proven on site. After piling, sample piles are tested with two complementary methods:

  • The PDA test (Pile Driving Analyzer, ASTM D4945) estimates a pile's bearing capacity from the stress waves recorded when the pile head is struck.[4]
  • The PIT test (Pile Integrity Test, ASTM D5882) checks the pile's integrity, such as cracks, breaks or a narrowing of the section. PIT does not measure bearing capacity, which is why the two tests complement each other.[5]

If the results show that additional piles are needed, that work is most efficient while the piling rig is still on site.

Pile joints

Piles 15 to 38 metres long usually cannot be delivered in one piece, so several segments are joined on site, typically by welding steel end plates. The strength of a joint depends heavily on the quality of the welding and workmanship, and SNI 8460:2017 requires pile joints to be accounted for in the design, unless a tested jointing system is used.[3]

Because every joint is a point that has to be made with great care, we use pile segments as long as site access and the piling rig allow, to keep the number of joints as low as possible. We also order a total pile length with a margin above the design depth, so that piling is not held up waiting for extra piles and no additional joints are needed.

Protecting neighbouring buildings

Piling causes vibration, and SNI 8460:2017 requires foundation work not to endanger surrounding buildings.[3] Before piling starts, we record the condition of neighbouring buildings with photographs and notes, including existing cracks, as a shared reference during construction. This protects your neighbours, and it also protects you from unfounded claims.

Five questions to ask your contractor

Before you appoint a contractor, ask these questions. The answers show how seriously your foundation is being planned.

  • Is the pile depth based on a soil investigation of my own plot, with boreholes and not only a cone penetration test?
  • Who designs the structure and foundations, and is downdrag included in the calculation?
  • What tests are carried out after piling, and will I receive the reports?
  • How long are the pile segments, and how many joints will each pile have?
  • How will neighbouring buildings be protected and documented?

Foundations are the hardest decision to change once a house is built. When you compare quotes, check that the pile size and depth match the structural consultant's drawings; our guide to comparing contractor quotes explains how. If you are planning a house in PIK or North Jakarta, see how we work, or talk to us at the planning stage.

References

  1. Rahardjo, P.P., Anggoro, B.W., & Wirawan, A. (2016). CPTu in Consolidating Soils. Proceedings of the 5th International Conference on Geotechnical and Geophysical Site Characterisation (ISC5).
  2. Kompas.com (7 January 2026). Interview with Yus Budiyono, researcher at BRIN's Research Centre for Limnology and Water Resources.
  3. Badan Standardisasi Nasional (Indonesian National Standards Agency). SNI 8460:2017 Persyaratan perancangan geoteknik (Geotechnical design requirements). Clauses 9.7.1.7 and 9.7.2.1 (negative skin friction); 9.4.4 (design report and joints); 9.5.3.3 (investigation depth); 9.2.3.1 (safety factor); 9.7.1 (surrounding buildings).
  4. ASTM D4945, Standard Test Method for High-Strain Dynamic Testing of Deep Foundations.
  5. ASTM D5882, Standard Test Method for Low Strain Impact Integrity Testing of Deep Foundations.
  6. Meyerhof, G.G. & Sastry, V.V.R.N. (1978). Bearing capacity of piles in layered soils. Canadian Geotechnical Journal, 15(2).

Frequently asked questions

How deep are house piles in PIK?

In our experience in PIK, about 15 to 38 metres. The exact depth must be set from a soil investigation of your own plot and a load calculation by the structural consultant, because the depth of strong ground varies from one site to another.

What is negative skin friction on a pile?

Negative skin friction, or downdrag, happens when the ground around a pile settles, for example because soft clay is still consolidating, and drags the pile down with it. Indonesia's SNI 8460:2017 requires this force to be included as a design load on the pile.

What is a lens in PIK soil?

A lens is a thin, discontinuous layer, usually dense sand or stiff clay, within soft clay. During piling, the stopping criterion (final set or jacking pressure) can be met on the lens, so the pile appears to have reached firm ground while soft ground remains below. Once the house is loaded, the pile tip can punch through and the pile settles. Investigating below the planned pile tips prevents this mistake.

What is the difference between PDA and PIT tests?

The PDA test (ASTM D4945) estimates a pile's bearing capacity. The PIT test (ASTM D5882) checks the pile's integrity, such as cracks or breaks, but does not measure capacity. That is why they complement each other.

Plan it right from the start

Tell us where your land is, its size, your architect or consultant (if you have one), and when you plan to start. Our team will review it and get back to you.